At a glance
Points of service
Digital provision points
Number of required documents
Fees
58.7 €
Deadline of completion
1 month
Description
Basic information
Competent body
Service / organizational unit of a authority entity
Provided to
Related links
Notes
Last update
03/12/2024
Application
Application Type
Submission by:
Submitted by:
Title
Notes:
What you will need
Means of authentication, identification and signature
Identification document, Identification with TAXISnet codes
-
1
1
The topographical chart of the area, in two copies, on a scale of 1:500, validated by the relevant u ...
Topographical drawing
The topographical chart of the area, in two copies, on a scale of 1:500, validated by the relevant urban planning service, as regards the permissible use of the station and the conditions of construction by the relevant urban service, showing the existing uses in a zone of 100 metres (m) perimeter of the stations plot or field.
Submission by: Submitted by the applicant (in person or by post)
Submitted by: Legal entities, Persons
Notes: If the station operates in an area outside an approved city plan, on a national or provincial road, the topography must be considered by the relevant Office of the relevant Regional Unit with the observation that the terms and conditions for the approval of the traffic connection of the station to the road are met, in accordance with the conditions of Article 24 of R.D. 465/1970, as applicable.
-
2
2
Approval of the traffic connection of the station. ...
Approval
Approval of the traffic connection of the station.
Submission by: Submitted by the applicant (in person or by post)
Submitted by: Legal entities, Persons
Notes: In accordance with Article 11 (c) and 15 (c) of PD 795/2004 (A 62), if the station is established in an area outside an approved town plan, its traffic connection with national or district routes shall be constructed in accordance with the terms and conditions of RD 465/1970 , as applicable. In the case of stations established in areas within an approved town plan, its traffic connection shall be formed in accordance with Article 11 (cf. 2 and 3), of RD 79/2004 (A’62), as applicable.
-
3
3
Written consent to the proper construction of the approved traffic connection. ...
Solemn Declaration
Written consent to the proper construction of the approved traffic connection.
Submission by: Submitted by the applicant (in person or by post)
Submitted by: Legal entities, Persons
Notes: The written consent shall be obtained by means of a solemn declaration by the competent engineer.
-
4
4
Architectural drawings in two copies ...
Architectural drawing
Architectural drawings in two copies
Submission by: Submitted by the applicant (in person or by post)
Submitted by: Legal entities, Persons
Notes: The architectural drawings relate to:
- (a) plan views of all levels and sites or buildings which make up the Station (i.e. office, cargo and luggage warehouses, any washing room);
- (b) indicative sections of the above buildings.
- (c) Main aspects of the above buildings.
- (d) General layout plan of all the building facilities of the Station, showing the entrances to the Station, access corridors, docks, parking areas and generally the whole operating layout of the Station.
-
5
5
Electrical drawings in two copies ...
Drawings / studies by an engineer / architect
Electrical drawings in two copies
Submission by: Submitted by the applicant (in person or by post)
Submitted by: Legal entities, Persons
Notes: The electromechanical (E/M) relates to:
- I. Complete electrical designs of buildings, with tables, cables, switches, power supply, microphone installations (if provided) which are accompanied by a complete technical description and specific computation issue.
- II. Complete ventilation drawings of the warehouse area accompanied by a full technical description and a separate calculation booklet.
- III. A complete electrical lighting plan of the surrounding area of the station, including the construction details of the cable routing, the laying of the lighting columns on the ground or the fixing of the luminaires to walls, any manholes and connecting mounds, accompanied by a full technical description and a separate set of calculations.
- IV. A complete water supply and sewerage drawing of the surrounding area, showing the respective networks and their route, the water companys meter, the location of the connection of the sewerage network to the city network, any necessary waste collectors, septic tanks, cesspools or watertight tanks and/or biological treatment. This plan shall include the same or be accompanied by detailed drawings of the manholes, pipes, water supplies and waste collectors.
-
6
6
Two-copy labelling plans ...
Drawings / studies by an engineer / architect
Two-copy labelling plans
Submission by: Submitted by the applicant (in person or by post)
Submitted by: Legal entities, Persons
Notes: Signalling drawings include vertical and horizontal marking, both in spite of the entrance-outlets of the station and within the station, i.e. vehicle driving arrows, warning signs, sound signals and any other material required to inform and guide the trader in the public and drivers.
-
7
7
General technical report of the engineer ιn two copies. ...
Drawings / studies by an engineer / architect
General technical report of the engineer ιn two copies.
Submission by: Submitted by the applicant (in person or by post)
Submitted by: Legal entities, Persons
Notes: The Engineers General Technical Report aims to identify the design auditor for the plant structure, the type to which it belongs, the key elements taken into account in the design, the basic components of the buildings and summarize the corresponding electromechanical installations. If the plant has a washing machine and/or lubricants, then the Report includes the corresponding chapters, as defined in Section 6 of the MODEL III of circular oik.13929/929/11.3.2014. The facilities with washing machines and/or lubricants must have the corresponding Operating Disclosure and comply with the terms and conditions of the Ministerial Decision No 56926/23 (Guideline B/23/1023).
-
8
8
Special projections for lifting and construction of scaled inspection levels in two copies ...
Drawings / studies by an engineer / architect
Special projections for lifting and construction of scaled inspection levels in two copies
Submission by: Submitted by the applicant (in person or by post)
Submitted by: Legal entities, Persons
Notes: Specific projections for lifting and construction of ramped levels of inspection shall be submitted if the Station includes such facilities.
-
9
9
Fire safety certificate ...
Fire safety certificate
Fire safety certificate
Submission by: Submitted by the applicant (in person or by post)
Submitted by: Legal entities, Persons
Notes: The Fire Safety Certificate shall be issued by the relevant fire department, in accordance with the applicable regulations, indicating its period of validity.
-
10
10
Solemn Declaration of the overseeing engineer. ...
Solemn Declaration
Solemn Declaration of the overseeing engineer.
Submission by: Submitted by the applicant (in person or by post)
Submitted by: Legal entities, Persons
Notes: In the Head of Statement, the engineer states that ‘the construction of the plant and the electromechanical installations were carried out in accordance with the approved designs and technical regulations and that the conditions and limitations of d.d. 79/2004 have been complied with when the work was supervised’.
-
11
11
Building licence and any other element attesting the legality of the building ...
Certificate from town planning
Building licence and any other element attesting the legality of the building
Submission by: Submitted by the applicant (in person or by post)
Submitted by: Persons
Notes: The building licence and any other element attesting the legality of the building may also be sought by the competent authority.
-
12
12
For the disclosure of changes/amendments, where applicable, supporting documents shall be provided. ...
Table / Statement / Catalogue (conditional)
For the disclosure of changes/amendments, where applicable, supporting documents shall be provided.
Submission by: Submitted by the applicant (in person or by post)
Submitted by: Legal entities, Persons
Notes: In the case of an announcement of changes/extensions/modifications of the premises of the Station, the relevant supporting documents relating to such changes/modifications shall be submitted for approval. According to par. 11, of the circular no. oik.13929/929/11.3.2014, before the implementation of the changes/extensions/modifications of the stations facilities, the new plans and the technical report of the requested changes and/or extensions with facilities provided for by the applicable provisions must be submitted to the competent authority, upon request of the interested party, for verification.
Document submitted under requirements: Yes
Document’s requirement: Administrative
Requirements
-
1
Company law
Business recommendation (individual, corporate)
- For company recommendation see link below
Link Link
-
2
Possession of passwords to enter software
Applicant must be TAXISnet code holder
Link Link
-
3
Technical
The notice of commencement of operation requires compliance with the conditions laid down in Articles 1, 3 and 4 of Article 10, Articles 11, 12 and 13 of Chapter B of Annex B to PD 79/2004 (FEK 62 A 2004), on the location of the station, on traffic regulations, as well as the installation of facilities, buildings, electromechanical equipment, marking, etc.
-
4
Technical
The required supporting documents as described in Annex III (Section 6. ‘Announcement of commencement of operation of a truck station for loading unloading goods without a fuel pump installation’), of circular No. 13929/929/11.3.2014 as applicable.
-
5
Technical
In the case of changes/modifications to the installations of the station, compliance with the requirements and conditions of Articles 1, 3 and 4 of Article 10, Articles 11, 12 and 13 of Chapter B of PD 79/2004 (FEK 62 A 2004), the location of the station, traffic arrangements, and the installation of facilities, buildings, electromechanical equipment, markings, etc.
Fees
-
1
Announcement of operation of a truck station.
58.7 €
e-Administrative Fee code 8258
Cost Calculation One-off
Method of Payment Bank cashier, Digital (debit / credit card), Digital (web banking), Hellenic Post
Type of Cost e-Administrative Fee
Fee Link Link
Related
Means of redress or appeal:
OtherSpecial administrative appeals - Applications for treatment (Article 227 of Law 3852/2010)
Rules concerning a lack of reply from the competent authority and the legal consequences for the use:
Tacit approval
NACE
- 52.29 Other transportation support activities
- 52.21 Service activities incidental to land transportation
Output & Results
Output
Steps
-
1
Commencement of Operation Announcement Procedure
Description The Notice of Commencement of Operation is made in accordance with the circular no. οικ.13929/929/11.3.2014, which simplifies the procedures of p.d. 79/2004.
Notes During the one (1) month period required for the issuance of the Certificate of Lawful Operation of the Station (if the requirements are met), the person concerned is prohibited from operating the Station.
-
2
Request for an Announcement - Protocol
Responsible for Implementation Competent Employee
Μethod of Implementation Manual Action
Description The application for the announcement of the operation of the truck stop is received by the competent Transport and Communications Department of the relevant Regional Unit, together with the required documents and is registered.
Notes Of the required supporting documents (Circular No. 13929/929/11.3.2014, Model III.6), two (2) copies of all drawings and technical reports for the construction of the activity/enterprise will be submitted. The first of the two copies shall be kept on file with the competent authority and the second shall be issued to the interested party along with the Certificate of Legal Operation of the station.
-
3
Verification of the completeness of the supporting documents
Responsible for Implementation Competent Employee
Μethod of Implementation Manual Action
Description Within five (5) working days of receipt of the notice, the official of the competent authority shall carry out a check of the completeness of the documents submitted, where appropriate.
Notes In case of no completeness (lack) of the supporting documents required, the Office responsible shall inform the person concerned in writing within five (5) working days of the absence of any of the supporting documents provided. The interested party will have to provide the supporting documents to continue the procedure for the issuance of the Certificate of Lawful Operation.
-
4
Certification of Opening Announcement
Responsible for Implementation Competent Employee
Μethod of Implementation Software action
Description In case that within five (5) days of the submission of an application for notice, the completeness of the required supporting documents is established, the person concerned shall be granted a Certificate of Initiation Notice.
Notes The Opening Announcement Confirmation is issued in accordance with Model II of Circular No. 13929/929/11.3.2014.
-
5
Non-fulfilment of supporting documents
Responsible for Implementation Competent Employee
Μethod of Implementation Manual Action
Description If, following the written notification of the interested party by the competent Service, for the incompleteness (lack) of the required documents, the interested party does not respond in order to provide the missing documents, the process of issuing a Certificate of Legal Operation is discontinued.
-
6
Examination of the suitability of supporting documents
Responsible for Implementation Competent Employee
Μethod of Implementation Manual Action
Description The competent Service, within one (1) month from the issuance of the Certificate of Submission of Notification of Commencement of Operation of the Station, proceeds to the examination and control of the supporting documents, in order to ascertain that all the legal requirements for the operation of the facility are met.
Notes Within twenty (20) calendar days from the date of issuance of the Certificate of Submission of Notification of Commencement of Operation, the competent department may request (by fax or e-mail) the applicant to provide additional information or clarifications on the documents already submitted, setting a deadline of five (5) calendar days.
-
7
Acknowledgement of the legal function of a Station
Description If all the legal requirements are met, the competent authority issues the Certificate of Legal Operation of the Station, according to Model IV of No. οικ. 13929/929/11.3.2014.
Notes The interested operator of the Station, in the case of implicit approval, i.e. after thirty (30) days from the issuance of the Certificate of Submission of the Notice of Commencement of Operation, may request the relevant Certificate of Legal Operation of the Station from the competent Service, in accordance with par. 4, of Article 10, of Law No. 10. 3230/2004 (FEK 44 A).
-
8
Prohibition of Station Operation
Responsible for Implementation Competent Employee
Μethod of Implementation Manual Action
Description If all the legal requirements are not met, or if it is not clear from the information submitted that they are met, the competent authority prohibits the operation of the business, informing the interested party in writing and stating the reasons. The notification must be made within one (1) month from the confirmation of the submission of the Notice of Opening of the business.
Notes The operator of the station concerned, if he considers that the operation of his activity has been prohibited, even though in his opinion he has submitted all the required documents, may appeal to the competent administrative bodies against the act of the administrative authority to which the Notice of the commencement of operation of the station has been submitted.
-
9
Changes/amendment procedure
Description For the notification of changes/modifications of Truck Stations for Loading / Unloading of Goods, the approval of the competent department of the planned changes, extensions, modifications, etc.
Notes For cases of change/modification, the procedure corresponding to that of the notification of the commencement of the activity, as defined in par. 1 of the last section "Transitional Stage" of the Circular No. οικ.13929/929/11.3.2014.
-
10
Receipt of Announcement of Changes/Amendments - Protocol
Responsible for Implementation Competent Employee
Μethod of Implementation Manual Action
Description Changes in relation to the originally approved plans, which require a change in some of the elements of the installation or an extension with installations provided for by the provisions in force, must be submitted before their implementation to the competent Service for verification, at the request of the interested party, the new plans, if applicable, the technical report and other supporting documents of the requested changes and / or extensions.
-
11
Control of Required Justifications
Responsible for Implementation Competent Employee
Μethod of Implementation Manual Action
Description The competent Service checks the new provided, if applicable, plans, technical report and other support documents of the requested changes and / or extensions, in order to approve them, if provided by the applicable provisions and if the legal requirements are met.
-
12
No Approval of Changes/Amendments of the Station
Responsible for Implementation Competent Employee
Description If the conditions for the change/modification of the stations facilities are not met or if they are not evident from the submitted supporting documents, the competent Service prohibits the approval of the changes, informing the interested party in writing and stating the relevant reasons.
-
13
New Verification of Legal Function - Approval of Changes/Amendments
Responsible for Implementation Competent Employee
Μethod of Implementation Manual Action
Description After the approval of the requested implemented changes and/or facilities, a new Certificate of Lawful Operation is issued, if after the examination and control of the above documents, it is established that all the terms and conditions of activity provided by the legislation in force for their approval are met.
Other information
Alternative titles
Official title
Languages supported
Ways of provision
Legislation
-
Law 4302/2014 (Government Gazette 225/Α)
Description Setting up logistics issues, excluding A category stations of PD 79/2004.
-
Law 3919/2011 (Government Gazette 32/Α) Articles 3
Description The principle of professional freedom, the abolition of unjustified restrictions on access to and exercise of professions; Articles 1, 2 and 3 lay down the conditions for the abolition of licensing procedures and the application of the 'Notification' procedure.
Legal references Link
-
Presidential Decree 79/2004 (Government Gazette 62/Α)
Description Definition of terms and conditions for the establishment and operation of long-distance bus stations and lorry stations for the loading-unloading of goods (car freight stations); The PD 79/2004 defines all the supporting documents required by the person concerned for the commencement of operation of these truck stations, as well as the technical conditions and requirements for their operation.
Legal references Link
-
Joint Ministerial Decision 81590/1446/3002/2015 (Government Gazette 3002/Β)
Description Simplification and integration of procedures of the Department of Vehicle Control and Installations of the Ministry of Infrastructure, Transport and Networks in the Points of Single Contact (EKE). In Paragraph 1 of that Decision it is stated, inter alia, that the procedure of the "Commencement of operation of truck stations for loading-unloading of goods, without fuel pump installations" may be carried out through the Citizens Service Centres (KEP) operating as Points of Single Contact (EKE).
Legal references Link
-
Circular 13929/929/2014
Description The circular relates to the commencement of operations of a vehicle service facility in accordance with the provisions of Law 3919/2011 as applicable. The circular describes the procedure for the notification of such installations and gives standard application forms for that procedure. In particular, on page 9 of the circular, for the truck service stations for the loading of goods, it is stated that: ‘In PD 79/2004 (A’62), as in force the reference to ‘installation permit’ and ‘operational permit’ in Articles 10, 15, 16 or elsewhere referred to.’ In paragraph 10 of the section "Procedure for the notification of the commencement of operations" of the Circular it is stated, inter alia, that: "... any of the undertakings in question that have fuel distribution facilities are not included in the facilities in question in this ...... and for the lawful operation of these facilities, an establishment and operating licence shall be granted in accordance with the applicable provisions. The licensing procedure for fuel disposal facilities (...) is governed by applicable legislation which is exempted from the application of Articles 2 and 3 of Law No. 3919/2011, as applicable. The same applies to any additional pump installations for the supply of fuel to vehicles at truck and intercity bus stations. The Circular was amended by Circulars No. 31927/2097/2014 (BIO1-6NN) and 46678/3013/1.8.2014 (705K1-0ΘΔ).
Legal references Link
ΑΔΑ ΒΙΚ51-ΕΞΝ
-
Circular 46678/3013/2014
Description Extension of application and amendment of the circular No. 13929/929/11-3-2014 on the commencement of operation of vehicle service facilities. It includes amendments to the initial circular, while paragraph 3 removes one of the supporting documents referred to in Model III.6, which relates to the budget of the required expenditure on the individual installations of the stations during their start-up procedure.
Legal references Link
ΑΔΑ 705Κ1-0ΘΔ
Categories
Τype of procedure
Trigger
Trigger (submission method)
Life events
Type
End of Process